What are you looking for?

Environment

Site rehabilitation and restoration

Liddell Ash Dam capping was slightly less than previous reporting period due to extended periods of wet weather. Ravensworth Ash Deposition to Void 5 was consistent with the previous reporting period.

Subsurface decommissioning of all 144 gas wells has been completed. The final three well surface locations (which comprised a total of 12 gas wells) are now under surface rehabilitation before being approved by government regulators and returned to their respective landowners. One further site has been fully rehabilitated and inspected by the govenment regulator and returned to the landowner, waiting on formal written approval from the government regulators.

Site

Activity

FY25

AGL Macquarie

Total area of ongoing capping and rehabilitation of Liddell Ash Dam and Ravensworth mine

Liddell Ash Dam - Cummulative total of 166 ha of Zone 1 Capping (1st 300mm) applied, 29 ha of Zone 2 Capping (2nd 300mm) applied. Ravensworth - approxiamtely 1.4 Mm3 of flyash deposited into Void 5 as part of rehabilitation to achieve a free draining final landform.

AGL Loy Yang

Total operational footprint

1188 ha

Progressive rehabilitation over FY25

29.54 ha

Cumulative total of rehabilitation since mining commenced

788.26 ha

Camden Gas Project

Number of the 144 gas wells and their sites that have been, or are in the process of being, decommissioned, rehabilitated, and returned to their respective landowners

144